Industry

Retainage and WIP for Massachusetts Contractors

What the state retainage law changes, and how to book it.

What the Massachusetts retainage law says

On private projects, Massachusetts limits how much an owner or contractor can hold back. The rule applies to private construction contracts where the prime contract has an original price of $3,000,000 or more. Projects of one to four dwelling units are excluded.

The main points
  • Retainage cannot exceed 5% of any progress payment
  • The prime contractor gives notice of substantial completion within 14 days of reaching it, and the owner has 14 days to accept or reject
  • Punch lists follow on a fixed timetable, from owner to prime and from prime to subcontractors
  • Once the conditions are met, retainage is to be released on a statutory schedule, less amounts held for incomplete or defective work
  • Subcontracts on a covered project follow the same limits

Know which projects are covered

The cap follows the prime contract, not your subcontract. A $200,000 subcontract on a $20 million private project is covered. Public work and smaller private jobs follow different rules, so record the retainage terms for each job when you set it up.

How retainage belongs on the balance sheet

Retainage is revenue you have earned and billed but cannot collect yet. Mixing it into ordinary receivables makes your aging report look worse than it is and hides the real collection problems.

  • Retainage receivable. A separate asset account. Each progress billing splits between accounts receivable and retainage receivable.
  • Retainage payable. A separate liability for amounts you are holding from subcontractors.
  • By job. Both balances tracked per project, so you know what releases when each job closes out.
  • Current versus long-term. Retainage on a job that will not close within twelve months may belong outside current assets. Banks and sureties notice.

Retainage and the WIP schedule

The work-in-progress schedule compares what you have earned on each job, based on cost incurred against estimated total cost, with what you have billed. The difference is an overbilling or an underbilling.

Retainage is part of billings. It does not reduce what you have billed, it only delays when you collect it. A common error is leaving retainage out of billed-to-date, which makes a job look underbilled and overstates revenue.

  • Bill the full progress amount, then show retainage as the portion withheld
  • Include retainage in billings-to-date on the WIP schedule
  • Update estimated cost to complete every month, not only at year-end
  • Investigate any job that moves from overbilled to underbilled. It is often a sign of cost overruns

What it does to cash

At 5%, a contractor doing $20 million a year in covered work has about $1 million out in retainage at a typical point in the year. That money has been earned, and the labor and materials behind it have been paid for.

Put retainage release dates in your 13-week cash forecast by job, tied to substantial completion. Then manage toward them: send the notice of substantial completion on time, close punch list items quickly, and invoice retainage the day it becomes billable. Contractors who treat closeout as an accounting task collect weeks earlier than those who leave it to the field.

Public work and certified payroll

Public projects in Massachusetts carry prevailing wage requirements, including certified payroll records submitted weekly to the awarding authority. That has two accounting consequences.

  • Payroll has to be coded by job and by trade classification, because the wage rate depends on both
  • Job cost reports should use the prevailing rates for public jobs, or your estimates on the next bid will be wrong

What your bank and surety will ask for

Bonding capacity and credit lines for contractors rest on a few documents: year-end financial statements, usually reviewed or audited by a CPA, a WIP schedule, and receivable and payable agings with retainage shown separately.

Keeping those current monthly, not once a year, is the difference between a quick renewal and a difficult one. A surety that sees a clean monthly WIP schedule extends more capacity than one that sees a single year-end report.

Common Questions

What is the maximum retainage in Massachusetts?

On private projects with a prime contract of $3,000,000 or more, retainage cannot exceed 5% of any progress payment. Residential projects of one to four units are excluded, and public projects follow separate rules.

Does the retainage law apply to subcontractors?

Yes. If the prime contract meets the threshold, the limits apply to subcontracts on that project regardless of their size.

How should retainage be recorded?

In separate accounts: retainage receivable for amounts held from you, and retainage payable for amounts you hold from subcontractors. Both should be tracked by job and shown apart from ordinary receivables and payables.

Is retainage included in WIP billings?

Yes. Retainage is part of what you have billed. Leaving it out of billings-to-date makes jobs look underbilled and overstates revenue.

A WIP Schedule Your Surety Will Trust